Solution Application
Applied Structures
Post Tension Beam
- This beam is strengthened with strong tensioned steel. With the addition of steel wires to concrete,
it improves the overall load-bearing capacity of the beam.
Work Process
-
Table Form Installation and
Level Adjustment 01 -
Beam Deck Installation and Preliminary Table Form Vertical Adjustment 02
-
Inspection, Concrete Placement, and Curing (14MPa, Dismantle after 3~4 Days) 03
-
Slab Deck Installation, Rebar Placement, Formwork Finishing / Structural Stabilization, and Jack Support Installation for Table Form Dismantling 04
-
Retain Jack Support 05
-
Table Form Dismantling, Movement, and Reinstallation (Repeat Step 1) 06